Armament work breakdown structure element

Assignment Help Operation Management
Reference no: EM131411341

Using the cumulative data provided from the Integrated Program Management Report, what is the cost performance index (CPI) for the Armament Work Breakdown Structure (WBS) element?

(IMAGE DESCRIPTION: WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510.)

Reference no: EM131411341

Questions Cloud

Relationship of the hr function to business strategy : Craft a list of questions to be used to interview a senior manager in HR to explore each interviewee’s thoughts about the changing role of HR, the relationship of the HR function to business strategy and the relationship between HR and the business o..
Some workers were starting work late and finishing early : After noticing that some workers were starting work late and finishing early, a department head wrote this message to subordinates: It is apparent that many of you are not giving the company a full day's work.
Describes the purpose of data validation checks : What is the role a Government technical team member plays in an update of a new Government estimate at completion (EAC)? Which of the following describes the purpose of data validation checks?
An electronic health record system : An Electronic Health Record System needs to be developed for a clinic that treats patients suffering from cancer. This clinic happens to be in a rural setting where most of the patients do not have health insurance coverage and depend heavily on Medi..
Armament work breakdown structure element : Using the cumulative data provided from the Integrated Program Management Report, what is the cost performance index (CPI) for the Armament Work Breakdown Structure (WBS) element?
Five levels of subordinate participation : There are five levels of subordinate participation in decision making ranging from highly autocratic (leader decides alone) to highly democratic (leader delegates to group): in your own discuss the following question in 350 word count. Address the fo..
Make business proposal and research literature : Make a Business proposal and research a literature for the topic. select and prepare a topic and "propose a fictional company" then incorporate their findings from their research and justify a business case for the use of the technology.
How can children protective service have finding of no fault : How can children protective services (CPS) have a finding of no fault when there is an injured child? An investigation of child injury is of the most significant action in child protection service.
Explain the general trend and trends within two subsets : Choose, at least, three areas and explain the general trend and trends within two subsets of the area (i.e., security has subsets of physical, perimeter, monitoring) over the last three years. Use at least one figure from Google Trends showing a ..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd