Consider the activity list in the table below. All duration estimates or estimated times are in days.

  1. Draw an AOA network diagram representing the project. The network should proceed from Node 1 to Node 9. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
  2. Identify all of the paths on the network diagram and note how long they are.
  3. What is the critical path for this project and how long is it?
  4. What is the shortest possible time needed to complete this project?

Reference no: EM131404020

Questions Cloud

Pre-qualified contractor or designer for non-public project : 1. Selection methods for choosing contractors is done by weighted criteria. Why would an owner choose to use a weighted criteria method to select a pre-qualified contractor or designer for a non-public project?
Pre-qualified contractor or designer for non-public project : 1. Selection methods for choosing contractors is done by weighted criteria. Why would an owner choose to use a weighted criteria method to select a pre-qualified contractor or designer for a non-public project?
How using robots will create better paying farm jobs : Explain how using robots will create better paying farm jobs.
Why number of combination be less than number of permutation : When we are considering n objects taken r at a time, with r 1, why will the number of combinations be less than the number of permutations?
Aoa network diagram representing the project : Draw an AOA network diagram representing the project. The network should proceed from Node 1 to Node 9. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Describe elements that enable employees to become empowered : Describe the four elements that enable employees to become empowered. Compare the five groups of needs in Maslow's theory with the three groups of needs in Alderfer's ERG theory.
What is the marginal product of the sixth farm worker : What is the marginal product of the sixth farm worker? If, when the price of asparagus rises to $3 a bunch, the farm hires eight workers, what is the marginal product of the eighth worker?
Time management instead of scope management : Answer the following item with complete sentences and paragraphs. Why do you think the defining activity is a process of time management instead of scope management?
In how many ways can his request be satisfied : If the purchaser of a vanity plate wants his first three positions to be ROY, in how many ways can his request be satisfied?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd