Analyze your schedule and network diagram

Assignment Help Project Management
Reference no: EM131987628

Project Assignment- Microsoft Project

You have just completed the project charter and scope statement. Now that you know what needs to be done, as the Project Manager, you are now ready to begin planning your project schedule.

You will have two deliverables to complete the assignment.

• Using MS Project, create a project schedule and align resources-35 points

Provide one deliverable (MS Project file).

To help guide you through this assignment, please follow the three-step process below.

Step 1: Create MS Project Schedule

The following steps should be followed when setting up your Course Project with Microsoft Project 2013 or 2016.

1. Set the basic project information

o Open MS Project.
o Click on File (top left), select Save as and enter the file name as (your name) cp1. For example, SmithJanecp1.mpp.
o Click on the Project area and select Project Information. In the Project Information dialogue box, set the start date of your project.
o Leave other dates as is. Click on OK.

2. Set basic Gantt chart format (use also for tracking Gantt chart view).

o Right click on the mouse in the gray area of the Gantt chart on the right side of the screen where the dates in month and days are for the menu and select Timescale.

o In the Timescale dialogue box:

- Select the Middle Tier tab set Units to Quarters.
- Select the Bottom Tier tab set Units to Months.

o Click on OK.

3. Setup the default task units to weeks

o Click File, and then click Options.
o In the Project Options dialog box, click Schedule.
o Under Scheduling options in this project, set the following.

- New tasks created select Auto Scheduled
- Duration is entered in select Weeks
- Default task type select Fixed Duration

o Click OK to close the dialog box.

4. Set up the Resource Sheet.

Once you have set the defaults, we are ready to move on. If you have not done so already, you need to create the project's work packages and activities from the Project's WBS. Once this is done, insert your project name, deliverables, work packages, and activities in the column Task Name in MS Project.

o Enter the task durations in the Duration Column.

o Enter the predecessor(s) for each task in the predecessors column. If there is no duration or predecessor listed, leave the column blank.

Note: If you do not see the Predecessors Column, move the vertical line between the Entry Form and the Gantt chart to the right to reveal the column. Click on the line and drag to move it. Columns can be expanded or contracted individually to accommodate information the same way column width is adjusted in MS Excel.

Analyze your Schedule and Network Diagram

To see the network diagram, click on View, then select Network Diagram. Activities on the Critical Path are outlined in red, while noncritical path activities are outlined in blue.

Step 2: Allocate Resources in the MS Project Schedule

Once you have the WBS created in MS Projects, you need to assign resources to each activity. Remember only assign resources to activities, not other items on the WBS. Before you can do this, you need to create a resources sheet in MS Projects. To create a Resource sheet, click on View, Resource Sheet. Enter the Resource name, whether it is a human resource, a cost, or a material. Once this is finished, one can tie these resources to individual activities. Don't worry about costs, as that is next week's work.

To assign your resources to the aligned tasks in MS Project, follow the steps below.

Assign hourly resources and costs to the tasks that you have already entered.

• Choose View-Gantt Chart. Place active window on the first task.

• Click on the Double Headed icon on the upper tool bar (Assign Resources), or click Alt-F10.

• In the resource assignment window, select the appropriate resource for each activity.

• Repeat for all resources and activities according to the Resource List above.

Analyze Your Resource Allocation and Assignments

There are several methods to check for over-allocated resources.

1. Click on View, Resource Sheet-Resource(s) in red color are over-allocated.

2. Click on View, Resource Usage-Resource(s) in red color are over-allocated resource(s) by date.

3. Click on Project, Reports. A dialog box appears, click on Assignments then Select. Then click the report for Overallocated Resources, and then Select to print or view.

4. Remember with resources you need to assign how much time (by a percentage) each resource will be allocated to each activity. Simply lowering a given percentage may clear an over-allocation, but in real life this is not possible. One must come up with a better method do clear resource over-allocations.

Reference no: EM131987628

Questions Cloud

Discuss the implications of the relative cultural dimensions : You are in the role of project manager for a coffee franchise global expansion project. You plan to expand into three different countries.
Perform at optimal levels and remain engaged : Leaders must often motivate team members to perform at their optimal levels and remain engaged.
Example of a poorly constructed problem statement : Provide an example of a poorly constructed problem statement. Explain why the statement is poorly written.
Compute the annual inflation rate : Compute the annual inflation rate, LaTeX: f f as a percentage for the entire 20-year period.
Analyze your schedule and network diagram : Analyze your Schedule and Network Diagram. Activities on the Critical Path are outlined in red, while noncritical path activities are outlined in blue.
Describe yourself in entrepreneurial terms : Describe yourself in entrepreneurial terms using the ideas that are discussed in your reading. Use the following attributes from below
Supplier is offering your firm cash discount : A supplier is offering your firm a cash discount of 2 percent if purchases are paid for within ten days; otherwise, the bill is due at the end of 60 days.
Average length of the firm short-term operating cycle : Estimate the average length of the firm’s short-term operating cycle. How often would the cycle turn over in a year?
Determine original cost and accumulated depreciation : For the equipment that was sold, determine its original cost, its accumulated depreciation, and the cash received from the sale

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd