Analyze your schedule and network diagram

Assignment Help Project Management
Reference no: EM131987628

Project Assignment- Microsoft Project

You have just completed the project charter and scope statement. Now that you know what needs to be done, as the Project Manager, you are now ready to begin planning your project schedule.

You will have two deliverables to complete the assignment.

• Using MS Project, create a project schedule and align resources-35 points

Provide one deliverable (MS Project file).

To help guide you through this assignment, please follow the three-step process below.

Step 1: Create MS Project Schedule

The following steps should be followed when setting up your Course Project with Microsoft Project 2013 or 2016.

1. Set the basic project information

o Open MS Project.
o Click on File (top left), select Save as and enter the file name as (your name) cp1. For example, SmithJanecp1.mpp.
o Click on the Project area and select Project Information. In the Project Information dialogue box, set the start date of your project.
o Leave other dates as is. Click on OK.

2. Set basic Gantt chart format (use also for tracking Gantt chart view).

o Right click on the mouse in the gray area of the Gantt chart on the right side of the screen where the dates in month and days are for the menu and select Timescale.

o In the Timescale dialogue box:

- Select the Middle Tier tab set Units to Quarters.
- Select the Bottom Tier tab set Units to Months.

o Click on OK.

3. Setup the default task units to weeks

o Click File, and then click Options.
o In the Project Options dialog box, click Schedule.
o Under Scheduling options in this project, set the following.

- New tasks created select Auto Scheduled
- Duration is entered in select Weeks
- Default task type select Fixed Duration

o Click OK to close the dialog box.

4. Set up the Resource Sheet.

Once you have set the defaults, we are ready to move on. If you have not done so already, you need to create the project's work packages and activities from the Project's WBS. Once this is done, insert your project name, deliverables, work packages, and activities in the column Task Name in MS Project.

o Enter the task durations in the Duration Column.

o Enter the predecessor(s) for each task in the predecessors column. If there is no duration or predecessor listed, leave the column blank.

Note: If you do not see the Predecessors Column, move the vertical line between the Entry Form and the Gantt chart to the right to reveal the column. Click on the line and drag to move it. Columns can be expanded or contracted individually to accommodate information the same way column width is adjusted in MS Excel.

Analyze your Schedule and Network Diagram

To see the network diagram, click on View, then select Network Diagram. Activities on the Critical Path are outlined in red, while noncritical path activities are outlined in blue.

Step 2: Allocate Resources in the MS Project Schedule

Once you have the WBS created in MS Projects, you need to assign resources to each activity. Remember only assign resources to activities, not other items on the WBS. Before you can do this, you need to create a resources sheet in MS Projects. To create a Resource sheet, click on View, Resource Sheet. Enter the Resource name, whether it is a human resource, a cost, or a material. Once this is finished, one can tie these resources to individual activities. Don't worry about costs, as that is next week's work.

To assign your resources to the aligned tasks in MS Project, follow the steps below.

Assign hourly resources and costs to the tasks that you have already entered.

• Choose View-Gantt Chart. Place active window on the first task.

• Click on the Double Headed icon on the upper tool bar (Assign Resources), or click Alt-F10.

• In the resource assignment window, select the appropriate resource for each activity.

• Repeat for all resources and activities according to the Resource List above.

Analyze Your Resource Allocation and Assignments

There are several methods to check for over-allocated resources.

1. Click on View, Resource Sheet-Resource(s) in red color are over-allocated.

2. Click on View, Resource Usage-Resource(s) in red color are over-allocated resource(s) by date.

3. Click on Project, Reports. A dialog box appears, click on Assignments then Select. Then click the report for Overallocated Resources, and then Select to print or view.

4. Remember with resources you need to assign how much time (by a percentage) each resource will be allocated to each activity. Simply lowering a given percentage may clear an over-allocation, but in real life this is not possible. One must come up with a better method do clear resource over-allocations.

Reference no: EM131987628

Questions Cloud

Discuss the implications of the relative cultural dimensions : You are in the role of project manager for a coffee franchise global expansion project. You plan to expand into three different countries.
Perform at optimal levels and remain engaged : Leaders must often motivate team members to perform at their optimal levels and remain engaged.
Example of a poorly constructed problem statement : Provide an example of a poorly constructed problem statement. Explain why the statement is poorly written.
Compute the annual inflation rate : Compute the annual inflation rate, LaTeX: f f as a percentage for the entire 20-year period.
Analyze your schedule and network diagram : Analyze your Schedule and Network Diagram. Activities on the Critical Path are outlined in red, while noncritical path activities are outlined in blue.
Describe yourself in entrepreneurial terms : Describe yourself in entrepreneurial terms using the ideas that are discussed in your reading. Use the following attributes from below
Supplier is offering your firm cash discount : A supplier is offering your firm a cash discount of 2 percent if purchases are paid for within ten days; otherwise, the bill is due at the end of 60 days.
Average length of the firm short-term operating cycle : Estimate the average length of the firm’s short-term operating cycle. How often would the cycle turn over in a year?
Determine original cost and accumulated depreciation : For the equipment that was sold, determine its original cost, its accumulated depreciation, and the cash received from the sale

Reviews

Write a Review

Project Management Questions & Answers

  Evaluate and discuss airport operator

APA format required responses are 750 words per questionwith in text citations and Reference Page 1 - Evaluate and discuss airport operator and AirportSecurity Coordinator (ASC) security responsibilities.

  Calculate stocks and capital budgets

Calculate Stocks and Capital Budgets - Can you help me get started with this assignment

  Your product were to move through the global economy

Hypothetically speaking, if your product were to move through the global economy, what are the different areas that your product would have to go through to get to its final destination? (For example, customs and distribution are areas to consider.) ..

  A flow chart as part of a six-sigma quality improvement

A flow chart as part of a six-sigma quality improvement process might be found in which DMAIC category

  Explain the triple constraint

Explain the triple constraint. What is the impact upon the triple constraint when new requirements are added to the project scope in the middle of project.

  Question 1a the requirement of a major and a minor project

question 1a the requirement of a major and a minor project is based on some criteria.itemise at least 5 such criteria.b

  Purchase of the product or service to your company

Presentation: Your assignment is to choose a products or services and develop a marketing initiative that if implemented might lead to purchase of the product or service to your company

  Activities of the project management office

What is the focus of the Managing Product Delivery (MP) process - What would typically be activities of the Project Management Office (PMO)?

  How are coke and pepsi using their web sites

How are Coke and Pepsi using their Web sites, www.coca-cola.com and www.pepsi.com, to promote their newest product offerings?

  Each record should have at least one primary key

Each record should have at least one primary key field specified. After identifying the records and their corresponding fields, draw an entity-relationship (ER)

  Since the hospitals project budgeting approach is under the

since the hospitals project budgeting approach is under the microscope due to several large public budget overruns

  What is the utilization rate for the bin area

what is the utilization rate for the bin area? what is the probability that there are more than three tucks in the system at any given time?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd