Reference no: EM131029084
A manager must decide how many machines of a certain type to buy. The machines will be used to manufacture a new gear for which there is increased demand. The manager has narrowed the decision to two alternatives: buy one machine or buy two. If only one machine is purchased and demand is more than it can handle, a second machine can be purchased at a later time. However, the cost per machine would be lower if the two machines were purchased at the same time.
The net present value associated with the purchase of two machines initially is $75,000 if demand is low and $130,000 if demand is high. The net present value for one machine and low demand is $90,000. If demand is high, there are three options. One option is to do nothing, which would have a net present value of $90,000. A second option is to subcontract; that would have a net present value of $110,000. The third option is to purchase a second machine. This option would have a net present value of $100,000.
a. Identify the choice that would be made using each of the four approaches for decision making under uncertainty.
i. Maximin
ii. Maximax
iii. Laplace
iv. Minimax regret
The estimated probability of low demand is 0.40, and the estimated probability of high demand is 0.60.
b. Analyze this problem using a decision tree. What would be your suggestion? How many machines should the manager purchase initially?
c. Compute the EVPI and interpret it.
d. Perform sensitivity analysis on P(high).
Administering certain cases in court of limited jurisdiction
: Whether a state court or a federal court, both court systems have a hierarchy that is followed, from courts of limited jurisdiction to the top appellate court in a state or the Supreme Court of the United States. What is the purpose of administering ..
|
Design for systems function using graphical user interface
: Your task is to develop and prototype a new interface design for the system’s function using Graphical User Interface. Include the same functions shown on page 361 plus possible messages during user interface such as error messages, confirmation, sta..
|
Preparing an inventory management plan for screwdrivers
: Storied Lane Components is preparing an inventory management plan for screwdrivers. They have a forecasted demand of 10,935 screwdriers per month with a MAD of 152 screwdrivers per month. The lead time to receive screwdrivers is 1 week(s) and they wo..
|
Low-fat healthful choices are an important current trends
: Revised this paragraph, Low-fat healthful choices are an important current trends. It's tatally amazing that there are as many as one in five U.S. consumers on a diet. That's why our menu should reflect low-calorie, healthful options that still taste..
|
Analyze this problem using a decision tree
: A manager must decide how many machines of a certain type to buy. The machines will be used to manufacture a new gear for which there is increased demand. The manager has narrowed the decision to two alternatives: Identify the choice that would be ma..
|
Firms capacity can be limited by members of its supply chain
: Performance or time targets for each major group of activities in a project are set during the planning phase of a project. In what way are projects and typical business activities similar? A firm’s capacity can be limited by members of its supply c..
|
Experiencing either excessive idle time for cashiers
: A small grocery store has a total of four regular checkout lines and one express checkout line. Recently on Sundays the store has been experiencing either excessive idle time for cashiers or excessively long customer waiting lines. Determine the curr..
|
Path-goal leadership questionnaire
: Examine your results from the "Path-Goal Leadership Questionnaire." What gaps or misalignments, if any, exist between the results of your assessment and how you perceive yourself through a lens of Path-Goal Leadership Theory? Explain. What strategies..
|
What is the critical path for the project