Reference no: EM132715634
On August 1, Rosa Co. had work in process inventory of 1,500 units which were 75% complete as of that date. During the month, the company started in process 5,000 units of product, 4,000 of which were completely finished during the period. The unfinished units were 2/5 complete of the end of the month. Other data pertaining to the month's production activities follow:
STANDARDS:
Materials 2 pcs. Per unit of product@ P4 per piece
Labor 3 hours per unit @ P7.50 per hour
Overhead 3 hours per unit @ P5 per hour
ACTUAL:
Materials 9,800 pcs. @ a total cost of P38,220
Labor 14,000 hours @ P7.75 per hour
Overhead P71,500
Budgeted production for the month was 5,000 units of product.
Required:
Problem 1: Compute and analyze the variances for all the manufacturing cost elements.