Problem: BOEING 787 DREAMLINER

The first Boeing 787 Dreamliner was delivered to Japan's ANA in the third quarter of 2011, more than three years after the initial planned delivery date. Its complicated, unique design (including a one-piece fuselage that eliminated the need for 1,500 aluminum sheets and 50,000 fasteners and reduced the resulting weight of the plane proportionally), promise of 20% increase in fuel economy and reduction in ‘out of service' maintenance time, and problems with early testing of the new design all contributed to the giant project's troubles. Delivery of Boeing's 787 Dreamliner project was delayed, in part, because of their global supply chain network, which was touted to reduce cost and development time. In reality, this turned out to be a major cause for problems. Boeing decided to change the rules of the way large passenger aircraft were developed through its Dreamliner program; rather than simply relying on technological know-how, it decided to use collaboration as a competitive tool embedded into a new global supply chain process. With the Dreamliner project, Boeing not only attempted to create a new aircraft through the innovative design and new material, but it also radically changed the production process. It built an incredibly complex supply chain involving over fifty partners scattered in 103 locations all over the world.

The goal was to reduce the financial risks involved in a $10 billion-plus project for designing and developing a new aircraft and reduce the new product development cycle time. It tapped expertise of various firms in different areas such as composite materials, aerodynamics, and IT infrastructure to create a network in which partners' skills complement each other. This changed the basis of competition to skill set rather than the traditional basis of low cost. In addition, this was the first time Boeing had outsourced the production on the two most critical parts of the plane- the wings and the fuselage. The first sign of problems showed up just six months into the trial production. Engineers discovered unexpected bubbles in the skin of the fuselage during baking of the composite material. This delayed the project a month. Boeing officials insisted that they made up the time and all things were under control. But next to fail was the test version of the nose section. This time a problem was found in the software programs, which were designed by various manufacturers. They failed to communicate with each other, leading to a breakdown in the integrated supply chain.

Then problems popped up in the integration of electronics. The Dreamliner program entered the danger zone when Boeing declared that it was having trouble getting enough permanent titanium fasteners to hold together various parts of the aircraft. The global supply network did not integrate well for Boeing and left it highly dependent on a few suppliers. This case clearly underscores the hazards in relying on an extensive supply chain in which information exchange problems may create extended problems and seriously compromise a company's ability to carry out business as planned. Creating a radically different process can mean encountering unexpected problems. In some cases, it would put a company so far behind their competition that they were doomed to fail. However, in this case, the major competitor to the Dreamliner, the Airbus 380 program, was also using a global supply-chain model, and its program was delayed by a couple of years. The result for Boeing was a much-anticipated plane with fuel economy and outstanding design that made the wait worth it, but the resulting design, a plane that holds up to 250 passengers, compared to the A380, which has a seating capacity between 525 and 853, was a major compromise.

Discussion Questions

1. Why did Boeing adopt the radical change approach for designing and developing the 787 Dreamliner? What were the risks? In your opinion, was it a good move? Defend your choice.

2. Using the Silo Perspective versus Business Process Perspective, analyze the Dreamliner program.

3. What are your conclusions about the design of the integrated supply chain? Give some specific ideas about what could have been done to integrate it better.

4. If you were the program manager, what would you have done differently to avoid the problems faced by the Dreamliner program?

Reference no: EM131882015

Questions Cloud

What are the key components of the architecture : Enterprise architecture (EA) at American Express was the framework the organization used to align IT and the business.
What criteria did Saab use in selecting infrastructure : Saab Cars USA, with its network of 212 dealerships and 30 service centers, dedicated itself to providing its customers a level of service reflective.
Examining the decentralized architecture : What, in your opinion, is the difference between a decentralized architecture and a centralized architecture? What is an example of a business decision.
What is the sr of the resulting portfolio : The stock and bond portfolios have a correlation of .55 and TB or risk free rate is 2%. What is the SR of the resulting portfolio?
Analyze the dreamliner program : Why did Boeing adopt the radical change approach for designing and developing the 787 Dreamliner? What were the risks? In your opinion, was it a good move?
What percentage of your money must you invest in the T-bill : If you desire to form a portfolio with an expected rate of return of 0.11, what percentage of your money must you invest in the T-bill and P?
What outside factors come together for Santa Cruz Bicycles : Bicycle enthusiasts not only love the ride their bikes provide, but they also are often willing to pay for newer technology especially when it will increase.
What is the SR for the portfolio : What is the SR for the portfolio P? What is the change in SR if the coefficient of correlation is changed to -0.20? Assume TB rate is 5%.
What will be the dollar values of your positions : You are considering investing $1,000 in a complete portfolio. What will be the dollar values of your positions in X, Y, and Treasury bills,

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd