Analyze projects and recommend project

Assignment Help Project Management
Reference no: EM1343454

1) You are the assistant to the CFO of ABC Inc. divisions A, B and C have ach proposed projects that require a $1,000,000 cash investment. The CFO has asked you to analyze the projects and recommend which project he should fund.

ABC Inc. has a required rate of return of 15% risk adjusted.

ABC Inc. always uses a tax rate of 40% in investment analysis.

Project A is a long lived project. Net Revenues (sales less operating costs) are expected to be $300,000 per year for 18 years. All of the investment will go into equipment that will be depreciated using the straight lime method over 10 years.

The equipment will have no salvage value at the end of 18 years.

Project B is a medium term project. Net revenues are expected to be $375,000 per year for 7 years. The investment is $800,000 in depreciable equipment and $100,000 increase in working capital, which will be recaptured at the end of the project and $100,000 in training. The equipment will be depreciated straight line over 7 years and will have a salvage value of $100,000 due to the value of the scrap metals in the equipment.

Project C is a short term project. Net revenues are expected to be $415,000 per year for 4 years. The investment is $400,000 in equipment that is depreciated straight line and has a salvage value of $50,000. The remaining $600,000 goes into working capital of which $500,000 will be recaptured at the end of 4 years.

Which project do you recommend?

Does your recommendation change if the required rate of return falls to 12%.

Reference no: EM1343454

Questions Cloud

What will be this value in si units : The density of mercury is 13.595 g cm -3  . What will be this value in SI units? Give the SI units and their symbols for the following physical quantities:
Risk analysis and the value of information : Construct a decision tree - Risk Analysis and the Value of Information
Project evaluation using the marr : You are curious as to how long you should keep the car and you will graduate soon and you do not want to keep the car longer than 4 years.
Project worth through present and annual worth : Assess project worth through Present and Annual worth - Evaluate which alternative to recommend by the PW method and the AW method.
Analyze projects and recommend project : The CFO has asked you to analyze the projects and recommend which project he should fund and aBC Inc. has a required rate of return of 15% risk adjusted.
Project management : Do you think by informing the customer that you need more time for a project or the quality of the system would be diminished, they will give you more time?
Sample question based on production management : How does this affect productivity measurement and the comparison of productivity between the U.S. and other countries?
Step-wise answer to production management : Explain how the organization's managers maintain competitive advantage and stay ahead of the competition.
Prepare the case for an optimistic sales manager : Prepare the case for an optimistic sales manager who suggests that you should move ahead with the FMS now

Reviews

Write a Review

Project Management Questions & Answers

  Five types of risk management techniques

Describe five types of risk and discuss management techniques for eliminating, reducing, or mitigating each type of risk type.

  Web infrastructure improvement project

Make policies and procedure to address organization web hosting needs in several locations within the organization.

  Solution to free cash flow

Solution to Free Cash Flow - what is the free cash flow from the project in year one

  Analyzing the budget and actual costs

An inexperienced project manager analyzed the budget vs. actual costs and found that project spending was 10% under budget and was overjoyed at such "good news."

  Differentiating primary and secondary research

Explain the difference between "primary" and "secondary" research.

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

  Contingency planning and risk identification

Explain how does risk identification help with project contingency planning and give an example of a specific contingency plan

  Minimum cost of crashing project

What is the minimum cost of crashing the following project by 4 days?

  Duration estimation techniques in project management

In a short response, describe the advantages and disadvantages for each of the five techniques. Include an example of when it is appropriate to use each technique.

  Nature of the problems the organization faces

What is the nature of the problems the organization faces and how severe are these problems?

  Explaining business-related topic of interest

You are welcome to survey the literature on a business-related topic of interest.

  Debtholders and shareholders

Which project do the debtholders prefer and which project do the shareholders prefer?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd