Analyze how many different estimating technique were discuss

Assignment Help Project Management
Reference no: EM131974837

Assignment

THE ESTIMATING PROBLEM

Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into Barbara's company, a committee composed mainly of senior managers reviews the RFP. If the decision is made to bid on the job, the RFP is turned over to the Proposal Department. Part of the Proposal Department is an estimating group that is responsible for estimating all work. If the estimating group has no previous history concerning some of the deliverables or work packages and is unsure about the time and cost for the work, the estimating team will then ask the functional managers for assistance with estimating. Project managers like Barbara do not often participate in the bidding process. Usually, their first knowledge about the project comes after the contract is awarded to their company and they are assigned as the project manager. Some project managers are highly optimistic and trust the estimates that were submitted in the bid implicitly unless, of course, a significant span of time has elapsed between the date of submittal of the proposal and the final contract award date. Barbara, however, is somewhat pessimistic. She believes that accepting the estimates as they were submitted in the proposal is like playing Russian roulette. As such, Barbara prefers to review the estimates. One of the most critical work packages in the project was estimated at twelve weeks using one grade 7 employee full time. Barbara had performed this task on previous projects and it required one-person full time for fourteen weeks. Barbara asked the estimating group how they arrived at this estimate.

The estimating group responded that they used the three-point estimate where the optimistic time was four weeks, the most likely time was thirteen weeks, and the pessimistic time was sixteen weeks. Barbara believed that the three-point estimate was way off of the mark. The only way that this work package could ever be completed in four weeks would be for a very small project nowhere near the complexity of Barbara's project. Therefore, the estimating group was not considering any complexity factors when using the three-point estimate. Had the estimating group used the triangular distribution where each of the three estimates had an equal likelihood of occurrence, the final estimate would have been thirteen weeks.

This was closer to the fourteen weeks that Barbara thought the work package would take. While a difference of 1 week seems small, it could have a serious impact on Barbara's project and incur penalties for late delivery. Barbara was now still confused and decided to talk to Peter, the employee that was assigned to do this task. Barbara had worked with Peter on previous projects. Peter was a grade 9 employee and considered to be an expert in this work package. As part of the discussions with Barbara, Peter made the following comments: I have seen estimating data bases that include this type of work package and they all estimate the work package at about 14 weeks. I do not understand why our estimating group prefers to use the three-point estimate. "Does the typical data base account for project complexity when considering the estimates?"

Asked Barbara. Peter responded: Some data bases have techniques for considering complexity, but mostly they just assume an average complexity level. When complexity is important, as it is in our project, analogy estimating would be better. Using analogy estimating and comparing the complexity of the work package on this project to the similar works packages I have completed, I would say that 16-17 weeks is closer to reality, and let's hope I do not get removed from the project to put out a fire somewhere else in the company. That would be terrible. It is impossible for me to get it done in 12 weeks. And adding more people to this work package will not shorten the schedule. It may even make it worse. Barbara then asked Peter one more question: Peter, you are a grade 9 and considered as the subject matter expert. If a grade 7 had been assigned, as the estimating group had said, how long would it have taken the grade 7 to do the job? "Probably about 20 weeks or so," responded Peter.

QUESTIONS

1. How many different estimating techniques were discussed in the case?

2. If each estimate is different, how does a project manager decide that one estimate is better than another?

3. If you were the project manager, which estimate would you use?

Reference no: EM131974837

Questions Cloud

Your total insurance needs using the dink method : Estimate your total insurance needs using the DINK method.
Purchased or leased on the basis of future worth analysis : If the company’s MARR is 18% per year, should the clamshell be purchased or leased on the basis of a future worth analysis?
First edition of book and second edition of book : The school classification (year in school) of survey respondents differed between the first edition of the book and the second edition of the book.
Write research report on company annual report : HI6026 - Audit, Assurance and Compliance Assignment. Write research report on a company annual report which is listed in ASX
Analyze how many different estimating technique were discuss : THE ESTIMATING PROBLEM- If each estimate is different, analyze how does a project manager decide that one estimate is better than another?
Confidence interval for the population proportion : In a survey of 2281 ?adults, 728 say they believe in UFOs. Construct a 90% confidence interval for the population proportion of adults who believe in UFOs.
Compute the optimal capital budget : Compute the optimal capital budget. What projects should be accepted?
Investigate the effects of family income : What statistical test should be used to analyze the data of the study? Why?
Develop an er model to represent the information requirement : SBM4102 Data and Information Management - develop an ER model to represent the information requirements for given case study

Reviews

Write a Review

Project Management Questions & Answers

  Determined the actual number of workstations

You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure

  What maximum limit l should be set

What maximum limit, L, should be set so that only 10% of the turtles captured have shell lengths greater than L?

  Changes in project plan

Changes In Project Plan - one of the risks you anticipated for the project was the late delivery of the prototype from the vendor

  What are the strengt and weaknesses of the compan

What are the strength & weaknesses of the company? Create a website that show the airport sleeping rooms selections, how to apply, pictures and promotion.

  How are financial models superior to other screening models

What are the benefits and drawbacks of the profile model for project screening? Be specific about the problems that may arise in identifying.

  Discuss the triple constraint of project management

Briefly explain in your own words the relationship between each element of the triple constraint of project management.

  Express the perimeter p as a function of the width

The area of a rectangle is 25 sq/in. Express the perimeter P( ) as a function of the width , and state the domain of this function.

  Project with real cash flows versus nominal cash flowscan

project with real cash flows versus nominal cash flowscan you think of a project for which it might be easier to

  How measurement and design errors affect respondent errors

Develop three recommendations to help researchers increase the response rates in direct mail and telephone-administered surveys.

  How would you accomplish just the right mix of socialization

How would you ensure that you maintain a productive relationship with the Meeting Rambler and that this person does not feel uncomfortable as a result of your discussion of their meeting rambling?

  What is the single most important component of building

3. In your opinion, what is the single most important component of building relationships within a project team? Why? 9. You are working for a multinational organization and need to relay information to Japan. Which communication method would you c..

  Compute the total costs incurred in january

How many units were transferred from the Packaging Department to the Finished Goods Department during the month - what were the equivalent units of production for direct materials and conversion costs for the month of January?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd