Reference no: EM132608324
The following data have been compiled for Gordon Ltd for March.
Conversion occurs uniformly throughout the production process.
Work in process, March 1st - 11000 units:
Direct material (100% complete) $ 24,200
Conversion (20% complete) $ 4,950
Balance in work in process, March 1st $ 29,150
Units started during March 110,000
Units completed during March and transferred out to finished goods inventory 88,000
Work in process, March 31st:
Direct material (100% complete) Conversion (33.33% complete) Costs incurred during March:
Direct material $ 217,800
Conversion costs:
Direct labour $ 58,080
Manufacturing overhead $ 116,160 $ 174,240
Total production costs incurred during March $ 392,040
Required: (where necessary round off all figures to two decimal places)
Question 1. Analyse the physical flow of units for March. Use the weighted average method of processing costing.
Question 2. Calculate equivalent units. Use the weighted average method of processing costing.
Question 3. Calculate the unit costs. Use the weighted average method of processing costing.
Question 4. Analyse total costs. Use the weighted average method of processing costing.