Allied distributing equipment

Assignment Help Operation Management
Reference no: EM132227973

ALLIED DISTRIBUTING EQUIPMENT, INC.

As the staff assistant to the marketing director of Allied Distributing Equipment, Inc. (ADE), you are to plan and schedule the marketing program for the introduction of a new conveyor system. Together with the marketing director, the sales manager, the advertising manager, and the technical director, you have identified four major parts of the program, and the major activities associated with each. These are described below, with activity identification numbers and durations following the activities in parentheses.

Salesmen Training

The required salesmen training program requires three phases. The first is a refresher course describing ADE’s other products and how the new conveyor system relates to them. The second phase communicates to the salesmen their role in the total marketing program to sell the new conveyor system including sales demonstrations and customer approaches. The third phase familiarizes the salesmen with the customer instruction manuals, which cover the technical aspects of the new conveyor system.

To save time training salesmen, the marketing director asked the sales manager to simultaneously prepare Phase I of the sales training program (1, 8 weeks) and select the salesmen to be trained (2, 2 weeks). These activities both begin at the start of the project you are to design. After their selection, the salesmen are relieved of their responsibilities in their territories and transported to the ADE home office training center (3, 4 weeks).

The salesmen should not arrive for the training program before Phase I is prepared. After it is prepared, and the salesmen have arrived, Phase I (training) is completed (4, 10 weeks). While the salesmen are completing Phase I, Phase II of the training program is prepared (5, 11 weeks). Training in Phase II cannot commence until it is prepared and approved. The marketing manager will not approve Phase II until the general marketing approach is determined.

After Phase I of the training program is complete, and Phase II is designed and approved, the salesmen can begin and complete Phase II (6, 12 weeks). At the conclusion of Phase II, the salesmen are issued copies of the customer instruction manuals on the new conveyor system, and Phase III of the program is then completed (7, 4 weeks). After the training program is complete, the salesmen return to their respective territories (8, 2 weeks), ready to begin their sales effort simultaneously with the national promotion campaign.

Marketing Staff Training

The first step in the project for the marketing staff is determining the general marketing approach (9, 10 weeks). When this is completed, the necessary marketing staff are selected (10, 4 weeks), and transported to the home office-training center (11, 2 weeks).

After the general marketing approach is determined, and while the marketing staff trainees are being selected and transported to the home office, specific training plans for the marketing personnel are consolidated (12, 2 weeks). After these plans are consolidated, a familiarization course for these staff members is designed (13, 8 weeks), and when the staff and the course are both ready, the staff is familiarized (14, 8 weeks).

Advertising Activities

After the general marketing approach is determined, advertising plans are firmed-up (15, 6 weeks). After advertising is firmed-up, a technical paper is prepared (16, 6 weeks) and printed in a professional journal (17, 8 weeks). Also following the firming-up of the advertising plans, national advertising is prepared (18, 13 weeks), approved (19, 5 weeks), and distributed to the proper media (20, 2 weeks).

Not until the marketing staff is trained, the professional paper is published, and the advertising distributed, is the national advertising to be released and printed by the media (21, 2 weeks). The national promotion campaign will not proceed further until the salesmen return to their territories.

Brochure and Manual Planning

After the advertising plans are firmed-up, a general brochure is drafted and approved (22, 4 weeks), following which, the layout of the brochure is designed (23, 5 weeks), and the brochure is printed (24, 3 weeks). As soon as the brochure is approved, the customer instruction manual is to be prepared (25, 3 weeks), approved (26, 1 week), and printed (27, 2 weeks).

Copies of the instruction manual alone are sent to the training center (28, 1 week) as soon as they are printed, for use in Phase III of the salesmen-training program. As soon as both the brochure and the manual are printed, they are packaged together and delivered to the marketing staff for general distribution (29, 8 weeks).

Your Job

Construct a network diagram for this marketing diagram, identifying the activity number for each arrow. Indicate on the diagram the activities on the critical path and the minimum duration required to complete the project.

Reference no: EM132227973

Questions Cloud

High number of managerial layers in organization : It is obvious from the high number of managerial layers in the organization that previous CEOs have not practiced the principle of.
Analyze the theory of emotional intelligence : Analyze the theory of emotional intelligence within the organization. Share an anecdote of how your (or a co-worker) demonstrated emotional intelligence.
How the novel is an example of modern literature : For this project assignment, you will submit your Literary Analysis paper on the assigned novel selected for the course, which should focus on three.
Discuss about a real company in the fast food industry : You have just been hired by (your selected company) as its new vice president of strategic planning. The corporation's performance in recent years as well as.
Allied distributing equipment : As the staff assistant to the marketing director of Allied Distributing Equipment, Inc. (ADE),
Write a targeting and positioning analysis for a gym : Write a targeting and positioning analysis for a gym (think about you start your own business). The response must be typed.
Chocolate making company schedule production : How should the chocolate making company schedule production to meet demand (what is the optimal batch size)?
Assess the impact of technology : Assess the impact of technology as a determinant of team behavior and performance of a virtual project team.
Identify the reason for the new start up : Identify the reason for the new start up. Discuss the qualifications of founders that start a media organization. Explain the function of each position within.

Reviews

Write a Review

Operation Management Questions & Answers

  Business simulations and assessments applications

Can you share 3 theoretical concepts or theories you applied to capsim (Business Simulations and Assessments Applications) during the simulation?

  Identify the components of information system

Identify the components of an information system (IS) using the five-component framework, and provide a brief summary of each.

  Companies tend to closely guard confidential information

Companies tend to closely guard confidential information, such as product measurement data on quality control charts, for example.

  Compete with the convenience of online retail

To compete with the convenience of online retail, the Mall of America offers a mix of sit-down dining, fast casual, and fast food dining choices.

  Project managers to resist changes to project baseline

How does a tracking gantt chart help communicate project progress? Why is it important for project managers to resist changes to the project baseline?

  Prepare a presentation about age discrimination

To begin, review the SLP materials related to Age Discrimination in the background material.

  Differentiate between venture capitalists and angels

What is the private equity market? How does it differ from other funding sources? Identify three different kinds of investors in the private equity market. Differentiate between venture capitalists and angels.

  Efforts to standardize parts succeeded to the point

Hahn Manufacturing purchases a key component of one of its products from a local supplier. The current purchase price is $1400 per unit. Efforts to standardize parts succeeded to the point that this same component can now be used in five different pr..

  Strategies that dont reduce project risk

Strategies That Dont Reduce Project Risk

  Strategic sustainability planning covers purpose and benefit

Strategic sustainability planning covers purposes and benefits, SWOT (strengths, weaknesses, opportunities, and threats) analysis for strategic sustainability planning, tactical plans, goals and indicators for goal achievement

  Describe the organizational structure

Describe the organizational structure of your selected organization. Compare and contrast that structure with two different organizational structures.

  How does the multi generational workforce impact training

How does the multi generational workforce impact training at your workplace?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd