1. All resource leveling techniques involve
A.Delaying noncritical activities
B. Delaying critical activities
C. Using negative slack
D. Both A and C are correct
E. A, B, and C are all correct
2. Resource leveling can provide
A. Lower peak demand
B. Reduced resource need over the life of the project
C. Reduced fluctuations in resource demand
D. Both A and B are correct
E. A, B, and C are all correct
3. In a resource-constrained project, the first priority in assign activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost
4. A project budget report is showing our project as spending $40,000. Which of the following is true?
A. We are spending less than we should for the project
B. We are doing a good job managing the project
C. We should check to see if all the bills have been paid
D. Both A and B are correct
E. We can't be sure how the project is going