Reference no: EM132198173
Based of the summary below...
I would like to start off by introducing myself as some may not be aware I am Devin and have recently accepted a position with SuperPacks as a project manager. SuperPacks has been awarded a delivery contract for a new product and I have been assigned as the project manager. I am looking forward to meeting everyone as well as working together to achieve success in our upcoming project.
SuperPacks has been given the task of creating a backpack for the U.S Army, Ground Forces and Special Operations with a budget of $1,500,00. The customers have provided two specifications; the backpacks include a built in refrigerated pouch and radio module. Our contract states that a total of 200 units need to be delivered by March 1, 2017 and we have year from today to deliver the first 100 units by September 1, 2016 and 50 units every three months after first delivery.
Initial program action items:
The following dates are projected milestone dates:
First Delivery: September 1, 2016
Second Delivery: December 1, 2016
Last Delivery: March 1, 2017
First milestone payment (from customer); October 30, 2016
Second milestone payment: January 30, 2017
Final milestone payment: May 30, 2017
Initial program review (at the customers site): November 16, 2015
Subsequent program reviews: 6 months after initial review May 16, 2016
As you see, we have a little over two months before we have our first meeting with the customers to review and approve the new backpacks. Our first goal is to research size, weight and materials to ensure the backpack is not only durable but it will also meet the needs for our customers.
Project Risks / Risk Mitigation strategies
Design: Providing a durable backpack to meet the needs of the customer; we will work closely with customers to ensure that the product meets their qualifications such as size and weight.
Financial: Obtaining materials and supplies to keep within budget to produce and manufacture product; working closely with suppliers and manufacturers to use quality materials to stay within our budget.
Technical: Providing refrigerated pouch and radio module that will work; research existing products that can be used or modified to meet the specific criteria.
Execution: end product meets all needs specified and can withstand different geographical locations as well as inclement weather; conduct testing with product to make sure that it withstands different weather conditions, weight limits and size limitations based on the customers use.
Contractual risk- Keeping on schedule with all milestones as well as being able to provide finished product based on the delivery dates; assign tasks to different teams and departments and communicate regularly as we moved forward while also scheduling milestones of our own to make sure there is enough time for any improvements or adjustments needed before delivering the end product.
Develop the project scope document to include the following information:
Project description
Project assumptions
Project goals
Project constraints (if any)
Project limitations
Project milestones
Project risks (initial assessment)
The Project Scope needs to be developed prior to any analysis of unexpected events.
Part 2 - Analysis of Unexpected Events
Four areas affected by these unexpected events.
Three of the areas of the project affected by the events should include changes to the budget, human capital, and impact to schedule.
Identify one additional area affected by these events.