Reference no: EM132668808
Extravagant Inc. is installing a new plant at its production facility. It has incurred these costs:
1 Cost of the plant (cost per supplier's invoice plus taxes) 2,500,000
2 Initial delivery and handling costs 200,000
3 Cost of site preparation 600,000
4 Consultants used for advise on the acquisition of the plant 700,000
5 Interest charges paid to supplier of plant for deferred credit 200,000
6 Estimated dismantling cost to be incurred after 7 years 300,000
7 Operating losses before commercial production 400,000
Required:
Problem 1: Advise Extravagant Inc on the costs that can be capitalized in accordance to IAS 16.