Address the deviation and the effect of each option

Assignment Help Other Subject
Reference no: EM133063260

PPMP20010 Executing and Closing Projects - Central Queensland University

Project Status and Exception Reports
Based on the real-life case study

Part 1 - Project Status Report using EVA

Project status reporting is the act of collecting, analysing, and distributing project information. Project information is distributed to many groups of stakeholders and should be adapted to provide information at an appropriate level, format, and detail for each type of stakeholder (PMBOK Guide, 2017, Section 10.2.2.5). Project status reports are time-based reports.

Case Study (Project) - Queensland health payroll system

WBS Codes Main Tasks & Sub-Tasks
1 Project Initiation
1.1 Business case& project procedures
1.2 Business Requirements, technical requirements & solution scope
2 Project realization blueprint
2.1 Project management plan
2.2 Organizational change management
2.3 Develop system environment set-up
3 Execution
3.1 System configuration
3.2 System development
3.3 Integration testing & quality check
4 Final Preparation
4.1 Testing & quality check (i.e. User Acceptance Test)
4.2 Training
5 Go Live & support
5.1 Production support
5.2 Project End
5.3 Project Documentation

2 GANTT CHART

This chart represents the original baseline plan for the project. The vertical shaded column between May.2008and Jun. 2008 is the current date (31stMay2008) for the status report.

3 VARIANCE ANALYSIS

This table contains the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) values. Costs given in the table below are fictitious and in millions of dollars for assignment purpose ONLY.

Calculate Schedule Performance Index (SPI = EV/PV) and Cost Performance Index (CPI = EV/AC) in percentages (%) for each main task and their sub-tasks. Also calculate overall CPI and SPI as of 31stMay2008and interpret these values in terms of project status (cost-wise and schedule-wise) on 31st May 2008.

Calculate overall SPI &CPI here and comment on the status of the project (cost and schedule wise) as of 31st May 2008. As per the Gantt chart above, add PVs till 31st May 2008 only.

4 ESTIMATE AT COMPLETION (EAC)
Estimate at Completion (EAC) is the expected total cost of the completing all work expressed as the sum of the actual costs to date and the estimate to complete (see PMBOK 2017 Table 7-1 Page 267).
Calculate EAC and interpret the result in terms of cost-overruns etc. Please mention whether re-baselining of the project is required and the impact on project cost. Provide discussion and support your arguments with evidence from the given data.

Provide the calculations and your commentary here

5 TO-COMPLETE PERFORMANCE INDEX (TCPI)

TCPI is a measure of cost performance that is required to be achieved with the remaining resources in order to meet specified management goals.TCPI is expressed as a ratio of the cost to finish outstanding work to the remaining budget (see PMBOK 2017 Table 7-13 and section 7.4.2.3).
Calculate TCPI and provide your commentarybased on TCPI value.

Provide the calculations and your commentary here

6 COST SUMMARY

Summarise the impact of the costs on the project tasks and explain if there is a need to re-define the risks (see PMBOK 2017 Chapter 11).

Provide commentary (i.e. over/underbudget) on every task listed in Section 1 above including re-fining any risks (you can make assumptions about the risks related the case study).

Provide commentaryabout here

7 FORECAST COMPLETION DATE

Even though a more accurate forecast completion date is derived from the updated schedule, the forecast duration could also be derived from the Schedule Performance Index (SPI) and can help forecasts the end date of the project (see AS 4817-2006 pp.13-15 Section 2.3.2).

Calculate the forecast completion date of the case study (project) using the overall SPI calculated in Section 3 above.

State whether re-baselining of the project is required and the impact on the project schedule.

8 MILESTONE REPORT

Milestones are events on a schedule which marks the completion of a key activity (Managing PRINCE2 (2017) Page 113 & 155).

Describe issues (if any) for the cost-overruns and schedule-delays for the tasks listed in Section 1 above and based on the data provided in Section 3 above.

Part 2 - Project Exception Report

1. PROJECT INFORMATION
An exception report is produced when a stage plan or project plan is forecast to exceed tolerance levels set. It is prepared by the project manager to inform the project board or the executive committee of the situation, and to offer options and recommendations for the way to proceed. (Managing Successful Projects with PRINCE2, 2017, Section A.10).

An exception report is event driven and is compiled by the project manager as soon as tolerances are to be exceeded. This report is to follow the PRINCE2 (2017) format for the exception reports, as described in Appendix A.10.

Please find a real issue (cost-overrun, behind-schedule etc.) from the case study (Queensland health payroll system) provided on Moodle and complete thisexception report template.

2. ESTABLISH THE NEED FOR AN EXCEPTION REPORT
Provide the motivation to compile and raise the exception report to the project board along with appropriate reasons for your decision.

3. EXCEPTION REPORT
Complete the report with all relevant and necessary information as per Appendix A.10 in the Managing Successful with RINCE2 (2017). Carefully study the derivation (inputs), format and presentation and quality criteria sections in Appendix A.10.

Describe the possible consequences in the context of the case study(project), its stakeholders'expectations, and challenges.

3.1 Exception title

An overview of the cost-overrun or behind-scheduleor an other exception being reported
3.2 Causes of the exception A description of the causes of a deviation from the current plan
3.3 Consequences of the deviation What the implications are if the deviation is not addressed for:

3.3.1the project

3.3.2the corporate, programme managementand the customer

3.4 Available Options

What 2-3 options are available to address the deviation (exception) and the effect of each option on the business case, risks, and tolerances.

3.5 Recommendation

Of the available options, which one is recommended, and why?

3.6 Lessons

What lessons can be learnt from this exception which might potentially be beneficial for this project or future project?

Note: Assessment 1 need to be done

Attachment:- Executing and Closing Projects.rar

Reference no: EM133063260

Questions Cloud

Calculate the total amount to be assigned : Calculate the total amount to be assigned to the cost of goods sold for the fiscal year ended September 30, 20-2, and ending inventory on September
Implications of treating human subjects : Evaluate the constructs of hypothesis testing and inferential analysis, and the two types of errors that can be made when carrying out tests of significance (se
How has globalization affected sport finance : How has globalization affected sport finance in the past 10 years? How might it affect sport finance in the future?
Determine the equilibrium price and quantity : Suppose the market demand and supply functions are QDS AB3Use graphs to support your answer C = 35,500 - 260P and Q = 80P + 10,680.
Address the deviation and the effect of each option : Calculate TCPI and provide your commentary based on TCPI value - Summarise the impact of the costs on the project tasks and explain if there is a need
General legal and regulatory requirements : Compare and contrast important market considerations for your selected market against those in the domestic market. Explain the similarities, differences, and c
Money supply multiplier : Explain why (just mathematically)k if people hold relatively more cash-that is, the currency ratio increases-the money supply multiplier gets smaller.
Prepare a Cash Budget for the quarter ending September : The cash balance at 1 July 2021 is expected to be $15,400. Prepare a Cash Budget for the quarter ending 30 September 2021
Migration between the two places in a graph : According to the Tiebout model, does Location A or Location B have the net fiscal benefit? Why?

Reviews

len3063260

1/8/2022 12:47:35 AM

It’s PPMP 20010 Executing and closing projects Assessment 1 to be done The assessment 1 templates, marking criteria, case study, and briefing slides are provided below. You must use the templates provided to complete this assignment.

Write a Review

Other Subject Questions & Answers

  Argument about government should legalize soft drugs

Argument about whether the government should legalize "soft" drugs (e.g. Marijuana/cannabis) for recreational usage as well as medical usage

  Evidence for delivering quality health care

The objective of this study was to explore nurses' awareness of, knowledge of, and attitude toward EBP and factors likely to encourage or create barriers .

  Describe the retrospective and prospective research designs

Describe the retrospective and prospective research designs. What are the benefits and problems of these designs

  Produce a climate change fact sheet

Produce a 2-PAGE climate change FACT SHEET that provides a clear, well-illustrated, thoroughly referenced, evidence-based argument to a non-specialist audience

  How much of your personal feeling should you share

BU450 The challenge for this chapter presents a case of a manager who must implement several unpopular changes that he/she does not agree with and that come on.

  Differences between conflict management and anger management

Define the differences between conflict management and anger management. How would you use each in order to help employees in a disagreement come to a successful resolution?

  Creating and formulating appropriate research design

Build appropriate research design suitable to the context - creating and formulating appropriate research design. To do this, you need to set clearly defined

  Challenges for the newly qualified registered nurse

Topic: At does the current academic literature state in relation to the nursing workforce and the challenges for the newly qualified Registered Nurse

  How social media impacts communication

In the first paragraph, state your thesis and provide a summary of your main topics discussing how social media impacts communication.

  How blockchain technology may affect the job functions

In chapter 1, the author presents several use cases for blockchain technology. Describe the use case that aligns most closely with your current job role.

  Write about a policy you would change

Write about A Policy You Would Change - Environmental Policy

  Write an essay on assault weapons or legal drinking age

Topics: Assault weapons OR Legal drinking age. This essay should be at least 750 words (about 3 pages double-spaced). Your essay should also include a title.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd