Activity on project schedule has these duration estimates

Assignment Help Operation Management
Reference no: EM13758275

1. A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. The duration of the project is:

2. A given project’s duration along its critical path is 33 days and the total slack for one of the activities is 1 day. The planned finish time for the project is:

3. An activity on a project schedule has these duration estimates: optimistic (a)=1, most likely(m)=2, and pessimistic (b)=5. The activities expected duration is:

4. An activity on a project schedule has these duration estimates: optimistic (a) =1, most likely (m) =2, and pessimistic (b) =5. The activity’s variance is:

5. A given projects expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates, what is the probability that the project will finish on or before 50 days?

6. A given project’s expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The projects standard deviation along its critical path is 2.03. The appropriate complete z value is:

7. A given project’s expected duration along its critical path is 32 days. The project’s standard deviation along its critical path is 4 days. What is the probability that the project will finish on or before 35 days?

Reference no: EM13758275

Questions Cloud

Annual reports for the coca-cola company and pepsico : Using 2007 annual reports for The Coca-Cola Company and PepsiCo, Inc., answer the following questions. Write these up in a Word document, clearly identifying your response to each lettered item. Show supporting calculations for the items lettered ..
Discuss a preschool classroom and a classroom for children : Discuss a preschool classroom and a classroom for children five years old or more. Describe how the environments should use the principle of age appropriateness
Core competencies and network-based strategies : How does Procter and Gamble Company address change; consider the use of BPM/BPR and other change processes. How is Procter and Gamble Company using synergies, core competencies and network-based strategies to achieve competitive advantage?
What element of establishing an organizational strategy : Satisfying the customers of an organization is a requirement for business success. Therefore, customer perceptions matter when trying to decide what products and services the organization will offer. What element of establishing an organizational str..
Activity on project schedule has these duration estimates : A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. A given project’s duration along its critical path is 33 days and the total slack for one of the act..
What is being done to address the issues you identified : What is the Americans with Disabilities Act (ADA)? How does the ADA address issues for the aging population?   What is being done to address the issues you identified
Paper on mobility-cdma and gsm : Discuss a minimum of three mobile web applications that are familiar or that you used regularly.
Write essay on analyze arrangement of classroom environment : write a 2-3 page essay where you will analyze the arrangement of the classroom environment and evaluate why this type of environment could effectively meet the individual needs of children with autism.
Chronic fatigue syndrom : Describe Chronic Fatigue Syndrom and its remedies

Reviews

Write a Review

Operation Management Questions & Answers

  What types of information does each tool collect

Select two to three areas of potential improvement for the organization you chose. Describe the data needed to monitor improvement. Identify and describe at least three data collection tools you can use to collect performance information. What types..

  How many units are needed to break

A manufacturing process has a ?xed cost of $150,000 per month. Each unit of product being produced contains $25 worth of material and takes $45 of labor. How many units are needed to break even if each completed unit has a value of $90?

  An enforceable promise? should itt have to honor

An enforceable promise? Should ITT have to honor the policy that layoffs would be done based on seniority? Why or why not? I am not asking for your opinion

  What is your sphere of influence in your organization

What is your sphere of influence in your organization? Based on this, what impact can you have on the implementation of your business plan?

  What is the average waiting time in line

What is the average waiting time in line? (Do not round intermediate calculations. Round your answer to 3 decimal places.)

  Problems associated with creating marketing plans

Identify and discuss the major problems associated with creating marketing plans

  Reduced revenue makes controlling costs all the more vital

Reduced revenue makes controlling costs all the more important. For each issue, Michael carefully makes a forecast based on sales data collected at each location

  Standards of performance

What standards of performance did your professor establish? How was your actual performance measured? How was your performance compared to the standards?

  Describe how the perpetual inventory system works

Describe how the perpetual inventory system works. What are some advantages of using the perpetual inventory system? Is it necessary to take physical inventory when using the perpetual system?

  What is the minimum number of service bays fast lube needs

what is the minimum number of service bays fast lube needs to achive an anticipated production of 200 cars per 8 hour day.

  What can management do to fight this discrimination and

there have been many media reports regarding the rise of discrimination against arab-americans in the united states

  Explain and perform many different channel functions

Explain and perform many different channel functions. have more control in the channel. can be more efficient. can save money

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd