A set large scale development projects

Assignment Help Project Management
Reference no: EM13808687

Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct

A - The third project takes 160 days

B - The fourth project takes 145.8 days

C - The fifth project takes 162 days

D - The eight project takes 131.2 days

E - None of them is correct

 

 

Reference no: EM13808687

Questions Cloud

The court held that lightle committed fraud : The court held that Lightle committed fraud by not telling the truth about the contract status of the house. Did he intend to deceive the buyer? Since Lightle was the representative of the sellers, the Leighs, why should he have any obligation to the..
Advantages and disadvantages of using the pert approach? : What would you consider as advantages and disadvantages of using the PERT approach?
Presenting this to a project team : Project Management:  Develop a 5-6 slide PowerPoint presentation. Explain the nature of project management, the role of the project manager, and the 3 factors that affect the success of a project.In the "notes" section of the slide write the commenta..
Create a total quality team : You are required to create a total quality team. When you complete your work, you are to present it to the board of directors for approval. Among the things you must consider: Who should make up the team? What size should the team be? From which depa..
A set large scale development projects : Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct A - The third pro..
Describe an ethical dilemma : 4. Describe an ethical dilemma that a project team member might face while being part of an IT project. Discuss how the project manager could aid in avoiding or resolving such a dilemma. Discuss where this dilemma falls within the PMI and ACM codes. ..
What is the retailers effective cost of trade credit : A large retailer obtains merchandise under the credit terms of 3/20, net 40, but routinely takes 60 days to pay its bills. (Because the retailer is an important customer, suppliers allow the firm to stretch its credit terms.) What is the retailer's e..
What is counts unlevered beta : Counts accounting has a beta of 1.25. The tax rate is 35%, and Counts is financed with 45% debt. What is Counts' unlevered beta?
Currently bonds with a similar credit rating and maturity : Currently bonds with a similar credit rating and maturity as the firm's outstanding debt are selling to yield 8.32% while the borrowing firm’s corporate tax rate is 34%. The after tax cost of debt for the firm is ________% Common stock for a firm tha..

Reviews

Write a Review

Project Management Questions & Answers

  Stage of the product life cycle

Question At which stage of the product life cycle is the traditional photographic products division at? What product and pricing strategies would you recommend for use for this product line to Lanen's management team?

  Project management and riskcomment on belowrisk management

project management and riskcomment on below.risk management is a major component of successful project management. from

  Five types of risk management techniques

Describe five types of risk and discuss management techniques for eliminating, reducing, or mitigating each type of risk type.

  Appraising cultural issues to avoid pitfalls

Appraise cultural issues to avoid pitfalls and manage international projects successfully.

  What was salems expected net present value for this project

Present value information is given below so what was Salem's expected net present value for this project

  Spotting irregularities useful for manufacturing companies

Besides spotting irregularities, like the case above, what are some other ways that ABC cost data are useful for manufacturing companies?

  Risk management is important factor in technology

Risk management is an important factor in SaveWithUs' effective use of technology.

  Skills for a successful project manager

Write an essay that explains and discusses the skills to be a successful project manager

  Explain the importance of a project kick-off meeting and

explain the importance of a project kick-off meeting and what needs to be reviewed in that meeting. describe a project

  Assignment on providing quality service

Normal 0 false false false EN-US X-NONE X-NONE Providing Quality Service.

  About international human resource management

Discuss the culture and socio-political background of the country you selected. Be sure to include a description of the legal and governmental systems.

  Details regarding production management1 what are the steps

details regarding production management1. what are the steps that an organization must follow to implement a tqm

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd