A project has several activities. These activities are shown in the table below, together with their time estimates (in weeks) and the crashing costs information:
Activity Normal Time Normal Cost Crash Time Crash Cost Immediate PredecessorsA 2 $50 1 $70 ---B 4 $80 2 $160 AC 8 $70 4 $110 AD 6 $60 5 $80 AE 7 $100 6 $130 BF 4 $40 3 $100 DG 5 $100 4 $150 C, E, F
A. What is the critical path when normal activities are used?
B. Evaluate the minimum total direct cost for each of the following project durations (based on the cost associated with each activity): 13, 14, 15, 16, 17, and 18 weeks.
American Express marketers say they do not use the percentage-of-sales approach to advertising budgeting because if sales decrease in the segment, so will their budget.
Is it possible for a project to have more than one critical path? Responsibilities of the project manager.
Despite the implementation of good disaster prevention procedures, normal business operations stop and what is the focus of disaster recovery in such a situation
Describe how a work breakdown structure can be useful during the estimating of a project budget
Speculate on at least two time management strategies you can implement to maximize the amount of time you have at your disposal everyday. Describe how these strategies might be implemented.
Why are accurate estimates critical to effective project management? Please explain in detail.
Explain why you chose the criteria you chose and describe the difference between primary and secondary research.
Matching the production rate to the order rate by hiring and laying off employees as the order rate varies is which of the following pure production planning strategies?
What is the difference between functional and dysfunctional conflict on a project?
project managementassume that an activity has a normal tune of 20 weeks a normal cost of 72000 a crash time of 16 weeks
consulting plan and recommendationsthe case recruiting brigade budget department where failures to obligate yearly
Why would a project be categorized by its risk class? What effect does this categorization have on the cost of capital?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd