Your task for Week 4 is to prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following:

  • A formal change request
  • An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only. Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.
  • A list of all the assumptions made
  • An analysis of risk factors due to the change request
  • A new project schedule that shows:
    • The additional time required
    • The additional labour cost
    • The new completion date
  • A statement of work for one contractor
  • A contract closure process description for one contractor
  • A project closure process description

The project details are as follows:

The Smiths decide to build a house on a piece of land that they have purchased. They have consulted with an architect and have the blueprints created. You are a general contractor and have agreed to build the house for them. The Smiths inform you that they had been considering the addition of an extra wing in the house but have now decided against it as the additional space is unnecessary. The original blueprints that the Smiths gave you did not have the additional wing.

You have projected that it will take you 12 weeks to complete the house. However, you need a buffer to accommodate the uncertain weather conditions, and you tell the Smiths that you will need 14 weeks. The Smiths are really anxious to move into their new house. Although they agree for 14 weeks, they also want to put in a penalty for late completion. You agree, provided they also put in a bonus for early completion. You reach an agreement with the Smiths, and the contract is signed. You have figured the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

Clear the site.

5

20

Dig the foundation and footings.

3

9

Install forms.

3

9

Pour concrete.

1

5

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

Build the floor.

1

5

Frame the first floor.

2

10

Build the second floor.

2

10

Frame the second floor.

3

15

Sheath the house.

3

12

Install windows and doors.

4

8

Install siding.

2

6

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

Lay the carpet.

2

6

Install the hardwood flooring.

3

6

Install trim.

3

6

Procure the certificate of occupancy.

5

0

Total

75

184

Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a projected difference in price and time for the addition.

You figure that to add the extra wing the following would be required in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

This is referred to as lag time

Remove forms.

1

2

Build the floor.

1

4

Frame the first floor.

1

4

Build the second floor.

1

4

Frame the second floor.

2

8

Sheath the house.

2

6

Install windows and doors.

2

4

Install siding.

1

3

Put up roof framing.

2

6

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

Install wiring.

2

4

Inspect the wiring.

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install the hardwood flooring.

Install trim.

1

3

Total

34

83

This new estimate to add the wing, assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this will be the most economical way to add the additional wing to the property. Another option would be for the project to continue as originally planned, and then add the wing after the Smiths have moved in. After considering both options, the Smiths choose to follow your recommendation to add the new wing now so that they move in when the whole house is complete. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

Remove forms.

1

2

Build the floor.

1.5

6

Frame the first floor.

1.5

6

Build the second floor.

1.5

6

Frame the second floor.

2

8

Add the sheath.

2

6

Install windows and doors.

2

4

Install the siding.

1

3

Put up roof framing.

2.5

7

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

1

0

Install wiring.

2

4

Inspect the wiring.

1

0

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install trim.

1

3

Total

38

90

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

F

Framer

20.00

F

Siding installer

20.00

W

Window/door installer

30.00

R

Roofer

20.00

P

Painter

20.00

E

Electrician

35.00

FL

Flooring installer

20.00

T

Trim carpenter

35.00

PL

Plumber

35.00

In this project, you will analyse the situation andthe effect of the change request on the schedule, cost, and features. The final project, due in Week 8, will be based on your answers for this week and for Week 6.

Please make sure that you cite and reference all your outside sources properly, as per the Harvard Referencing System.

Reference no: EM13751893

Questions Cloud

Effect on return on equity of raising capital through debt : Debt has deadlines. Deadlines can be missed. Common stock lasts indefinitely. The higher percentage of resources raised from debt, the higher percentage resources subject to deadlines, hence risk. What is the effect on return on equity of raising cap..
Governance and fraud in health care organizations : Governance and Fraud in Health Care Organizations - Legal and Ethical Responsibilities - Management's Financial responsibility and consequences of a violation.
Instrument divisions income from operations increase : Materials used by the Instrument Division of Dart Industries are currently purchased from outside suppliers at a cost of $180 per unit. However, the same materials are available from the Components Division. How much would the Instrument Division's i..
Why you think we are difficult time recover from depression : With our vast resources today, why do you think we are having such a difficult time recovering from the depression of 2008?
A formal change request : Prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following: A forma..
Intermediate products should be processed further : Beets 'R' Us processes sugar beets in batches that it purchases from farmers for $57 a batch. A batch of sugar beets costs $12 to crush in the company's plant. Two intermediate products, beet fiber and beet juice, emerge from the crushing process.
Net cash flow for the last year of the computers useful life : Avis Corporation currently records $4,000 of depreciation each year on the computer that it uses for its major data processing needs. The computer currently has one more year of useful life left and it will have a salvage value of zero at the end of ..
What was the nature of massachusetts bay colony : What was the nature and character of Massachusetts Bay Colony Plymouth in Massachusetts, and the establishment of Maryland Based on your reading of the articles?
Examine the concepts of managing operations : Examine the concepts of managing operations as they apply to the production of goods and services - Apply the appropriate operations tools to aid in decision-making and optimize performance.

Reviews

Write a Review

Operation Management Questions & Answers

  Commissioner of public works

A town's department of public works is concerned about adverse public reaction to a sewer project that is currently in progress. Because of this, the Commissioner of Public Works

  What action can the provider take to ensure payment

This implies that the procedure performed is not supported by the diagnosis code. What action can the provider take to ensure payment?

  Explain expanding company''s manufacturing operation

Jan has been selected to implement her company's decision to expand her company's manufacturing operation into a new location. Six months into this project, the building has been completed, and machinery installed. However, Jan has been unable to ..

  Company competitive advantage please respond to the

company competitive advantage please respond to the followingbullpropose two ways that a company can gain a competitive

  Compute the optimal size of production run

The 3M incorporate produces solar cell panels, and the production rate can be 8,000 pieces per day. The demand for the solar panel is 30,000 pieces per month.

  Aspect of e-collaboration orknowledge management

Describing on aspect of e-collaboration orknowledge management. Summarize the article(s) andprovide your own perspective, and then browse through the other student posts to learn about other related technologies/uses.

  The decision-making process

How did you go about making the decision? Apply the steps of the decision-making process. Critique your decision approach. What were the strengths and weaknesses? Did you involve supervisors, coworkers, or employees? If so, how and in what capacit..

  Should the discount be taken

Cesar Rogo Computers, a Mississippi chain of computer hardware also software retail outlets, supplies both educational also commercial customers with memory also storage devices.

  Explain why do you think starbucks has now elected to expand

Explain why do you think Starbucks has now elected to expand internationally primarily through local joint ventures, to whom it licenses its format, as opposed to a pure licensing strategy.

  Determine the cycle time

Westside Auto purchases a compant used in the manufacture of automobile generators directly from the supplier. Westside's generators production operation which is operated a constant rate.

  What is outsourcing

What is outsourcing? And do you know of any related off-shoring issues, which pertain to the economy in the USA?

  Why capitalism has changed

Does the story of the American fur company hint at how and why capitalism has changed and has been changed over the years?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd