Project Crashing Assignment Help

Assignment Help: >> Project management >> Project Crashing

Project Crashing

In the event of the project's expected time of completion being more than the desired time, an attempt is made to reduce the time involved in some of the activities so that the project is completed on time. This process of reducing the time of the project by reducing the scheduled time of some of the activities is called crashing. Project crashing is accomplished by subcontracting, overtime, extra shifts, increasing the number of workers, additional capacity installation, etc. The key objective is to reduce the project time as much as possible with minimal expenditure. As these approaches have significant cost implications, operations managers analyze the time-cost trade-offs and reduce the project duration with minimal increase in costs. The steps involved in this project crashing are described below:

  1. First, identify the normal cost (estimated cost requirement for finishing activity in normal time) and crash cost and time (estimated cost requirement for finishing activity in crash time or reduced time).

  2. Identify the critical path and calculate new time-cost ratio for each activity based on the crash time and cost. Though the relationship is not linear, we assume a linear relation for simplicity and calculate the per unit crash cost as

  2305_project crashing.png

     3. Highlight the activities on the critical path with the smallest time-cost ratio and crash those activities. Crash the        selected activity to the maximum possible extent until one of the conditions given below is satisfied.

  • The activity time is at its minimum possible value.
  • The time reduced is equal to the smallest slack value of the non-critical activities.
  • The reduced time is equal to the desired project completion time.
  • After crashing, if the critical path changes, then the crash time is calculated based on the new critical path.

     4. Repeat the steps 2-3 till the project duration is crashed to the desired new level.                  

Problem 

Based on the information given in the following table, identify the number of days by which the project can be crashed and the total cost of crashing.

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

1-2

2

2

1000

1000

1-3

4

3

3000

3500

2-4

4

2

4000

6000

3-4

3

2

2000

3000

Solution

  1. Draw a network diagram using the normal time and calculate earliest and latest  times. From the Figure (a) we can see activities 1-3 and 3-4 are on the  critical path.

Figure a

320_network diagram.png
  1. Calculate the time cost ratio of each activity.

Time cost ratio =

234_project crashing.png

 

Activity 1-2 cannot be crashed.

Time cost ratio (1-3) = (3500-3000)/(4-3) = 500

Time cost ratio (2-4) = (6000-4000)/(4-2) = 1000

Time cost ratio (3-4) = (3000-2000)/(3-2) = 1000

  1. The critical path activity with smallest time cost ratio is selected and crashed. The activity 1-3 on the critical path has the smallest time cost ratio and it can be crashed by a day. This crashing will increase the project cost by Rs 500 and reduce the project duration from 7 days to 6 days.

  2. The network diagram for the new schedule is given in Figure b. As a result of the crashing, we now have two critical paths 1-2, 2-4 and 1-3, 3-4. As activities 1-2 and 1-3 cannot be crashed further, we have to crash the activities 2-4 and 3-4. Activity 3-4 can be crashed by a day and activity 2-4 can be crashed by two days. As crashing activity 2-4 by two days will not affect the project duration, both activities 3-4 and 2-4 are crashed by one day each.

Figure b                  

785_network diagram1.png

      5. The final network diagram is shown in Figure c. The final project duration is reduced to 5 days and the total cost of crashing = 500 +1000 +1000 = 2500.  

Figure c                

6_network diagram2.png

Email based Operations Management assignment help - homework help at Expertsmind

Are you searching Operations Management expert for help with Project Crashing questions?  Project Crashing topic is not easier to learn without external help?  We at www.expertsmind.com offer finest service of Operations Management assignment help and Operations Management homework help. Live tutors are available for 24x7 hours helping students in their Project Crashing related problems. We provide step by step Project Crashing question's answers with 100% plagiarism free content. We prepare quality content and notes for Project Crashing topic under Operations Management theory and study material. These are avail for subscribed users and they can get advantages anytime.

Why Expertsmind for assignment help

  1. Higher degree holder and experienced experts network
  2. Punctuality and responsibility of work
  3. Quality solution with 100% plagiarism free answers
  4. Time on Delivery
  5. Privacy of information and details
  6. Excellence in solving Operations Management questions in excels and word format.
  7. Best tutoring assistance 24x7 hours

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd