In project management, slack or float is the amount of time that a task in a project network can be detained without causing a delay to:
Subsequent tasks known as free float
Project completion date known as total float
An activity on critical path has zero free float, but an action that has zero free float may not be on the vital path. Total float is linked with the path. If a project network chart or diagram has 4 non-critical paths then that project would have 4 total float values. The total float of a path is the combined free float values of all activities in a path.
The total float represents the schedule flexibility and can also be evaluated by subtracting early dates from late dates of path completion.
Float Management - Online Tutoring - Assignment Assistance
We at Expertsmind.com offer Float Management homework help, Float Management free tutorials and assignment assistance and Float Management based question's answers by help of qualified and experienced finance tutors. We make easy Float Management based assignments and homework for you with conceptual Cash Management theory.
ExpertsMind.com - Float Management Assignment Help, Float Management Homework Help, Float Management Assignment Tutors, Float Management Solutions, Float Management Answers, Cash Management Assignment Tutors